PROJECT NAME: LOG – 68 – 5.82 - Complex Urban Highway

CLIENT: City of Bellefontaine, Ohio

PROJECT COST: $7,500,000

PROJECT DESCRIPTION: Project included the widening of an existing 3 lane facility to a 5 and 4 lane section. Project length was greater than 2 miles. The US 68 project included the realignment of an offset intersection, traffic volume projections, a signal warrant at the realigned intersection, and a signal removal study, in addition to all surveying and roadway design. The project also included design of five mast arm signals, evaluating turn volumes for permissive or protected control, interconnection, and an on-street master. This project included right-of-way plan preparation and had more than 90 property owners. This project was considered by ODOT to be a complex roadway design project.